New Please be informed that the The last date for submission of Quarterly Update of Registered Real Estate Projects is hereby extended tillĀ 28.02.2025 as per the order enclosed herewith. Click here to view the order ;  All promoters are directed to comply with the order of WBRERA vide no. 1986-RERA/L-01/2023 dated 06.12.2024 regarding Quarterly Update of Registered Projects and other instructions mentioned in the said order. Click here to view the order

MANAKAMNA 24

Project Status as on Quarter ending 31-12-2019
Updated as on 11-01-2020

Booking Status

  • Residential Apartments Booked
    132

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    98

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
DAWN 1 Under Construction
DAWN 2 Under Construction
DAWN 3 Under Construction
DAWN 4 Under Construction
DAWN 5 Under Construction
DUSK 1 Under Construction
DUSK 2 Under Construction
DUSK 3 Under Construction
DUSK 4 Under Construction
DUSK 5 Under Construction
TWILIGHT 1 Under Construction
TWILIGHT 2 Under Construction
TWILIGHT 3 Under Construction
TWILIGHT 4 Under Construction
TWILIGHT 5 Under Construction
SUNSHINE 1 Under Construction
SUNSHINE 2 Under Construction
SUNSHINE 3 Under Construction
SUNSHINE 4 Under Construction
SUNSHINE 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 DAWN
2 DUSK
3 TWILIGHT
4 SUNSHINE

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction DAWN (Passage)
2 Under Construction DUSK (Passage)
3 Under Construction TWILIGHT (Passage)
4 Under Construction SUNSHINE (Passage)
5 Under Construction LANDSCAPE AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download