New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

DWARIKA HEIGHTS

Project Status as on Quarter ending 30-09-2023
Updated as on 30-04-2025

Booking Status

  • Commercial Unit Booked
    81

  • Basement Parking Booked
    7

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Elevated Ground Floor 1 Completed With CC
Block 1 1 Completed With CC
Block 1 2 Completed With CC
Block 1 3 Completed With CC
Block 1 4 Completed With CC
Block 1 5 Completed With CC
Lower Ground Floor 1 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Not Yet Started

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area, Parking & Elevation

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download