| 1 |
Plumbing work completed |
|
| 2 |
External paint done, sanitary fittings completed in all flats, electrical work almost completed |
|
| 3 |
Excavation completed. Plinth level done fully. Roof casting done. Internal wall plaster in progress |
|
| 4 |
Flat G to M work in progress |
|
| 5 |
A to F 1st to 4th floor-90% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on |
|
| 6 |
A to F 1st to 4th floor-90% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on |
|
| 7 |
A to F 1st to 4th floor-95% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on |
|
| 8 |
Common area workin progress |
|