New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

CENTURY MANSION

Project Status as on Quarter ending 30-09-2025
Updated as on 05-10-2025

Booking Status

  • Residential Apartments Booked
    0

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Plumbing work completed
2 Excavation completed. Plinth level done fully. Roof casting done. Internal wall plaster in progress
3 Flat G to M work in progress
4 A to F 1st to 4th floor-90% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on
5 A to F 1st to 4th floor-90% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on
6 A to F 1st to 4th floor-95% work completed. G to M- Work in progress. Brick & plaster work is going on. Putty & tiles work is going on. Electrical & plumbing work is going on
7 Common area workin progress

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common area boundary work in progress
2 Under Construction PCC & boundary work is done. Tiles, paint, electrical, plumbing work is pending
3 Under Construction PCC & boundary work is done. Tiles work is going on. electrical, plumbing work is in progress. Paint is pending

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download