Project Status as on Quarter ending 30-09-2023
Updated as on 24-10-2024

Booking Status

  • Residential Apartments Booked
    40

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    21

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 complete
2 complete

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC complete
2 Completed With CC complete

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download