Ashiyana Heights Phase II

Project Status as on Quarter ending 30-09-2024
Updated as on 06-10-2024

Booking Status

  • Residential Apartments Booked
    53

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    35

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 - Ground Floor-Commercial 1 Under Construction
Block 1 - 1st to 8th Floor-Residencial 1 Under Construction
Block 1 - 1st to 8th Floor-Residencial 2 Under Construction
Block 1 - 1st to 8th Floor-Residencial 3 Under Construction
Block 1 - 1st to 8th Floor-Residencial 4 Under Construction
Block 1 - 1st to 8th Floor-Residencial 5 Under Construction
Block 1 - 1st to 8th Floor-Residencial 6 Under Construction
Block 1 - 1st to 8th Floor-Residencial 7 Under Construction
Block 1 - 1st to 8th Floor-Residencial 8 Under Construction
Block 3 - 1st to 8th Floor- Residential 1 Under Construction
Block 3 - 1st to 8th Floor- Residential 2 Under Construction
Block 3 - 1st to 8th Floor- Residential 3 Under Construction
Block 3 - 1st to 8th Floor- Residential 4 Under Construction
Block 3 - 1st to 8th Floor- Residential 5 Under Construction
Block 3 - 1st to 8th Floor- Residential 6 Under Construction
Block 3 - 1st to 8th Floor- Residential 7 Under Construction
Block 3 - 1st to 8th Floor- Residential 8 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Renewable Energy
2 Emergency Evacaution
3 Water Facilities
4 Fire Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started Lift
4 Not Started Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download