New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

MAYA APARTMENT

Project Status as on Quarter ending 30-09-2025
Updated as on 06-10-2025

Booking Status

  • Residential Apartments Booked
    0

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Work completed. Painting work also completed
2 Excavation and foundation work completed
3 All roof casting work comleted
4 Internal and External plaster and other work almost on the verge of completion
5 All window grill has been fixed
6 Electrical metre and transformer work in progress, Outside painting work is pending

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Construction work of common area are in progress

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download