WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

Townhouse Phase II

Project Status as on Quarter ending 31-03-2025
Updated as on 04-04-2025

Booking Status

  • Residential Apartments Booked
    32

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 29 - DUPLEX 1 Under Construction
BLOCK 29 - DUPLEX 2 Under Construction
BLOCK 29 - DUPLEX 3 Under Construction
BLOCK 29 - DUPLEX 4 Under Construction
BLOCK 30 - DUPLEX 1 Under Construction
BLOCK 30 - DUPLEX 2 Under Construction
BLOCK 30 - DUPLEX 3 Under Construction
BLOCK 30 - DUPLEX 4 Under Construction
BLOCK 31 - DUPLEX 1 Under Construction
BLOCK 31 - DUPLEX 2 Under Construction
BLOCK 31 - DUPLEX 3 Under Construction
BLOCK 31 - DUPLEX 4 Under Construction
BLOCK 32 - DUPLEX 1 Under Construction
BLOCK 32 - DUPLEX 2 Under Construction
BLOCK 32 - DUPLEX 3 Under Construction
BLOCK 32 - DUPLEX 4 Under Construction
BLOCK 42 - DUPLEX 1 Under Construction
BLOCK 42 - DUPLEX 2 Under Construction
BLOCK 42 - DUPLEX 3 Under Construction
BLOCK 42 - DUPLEX 4 Under Construction
BLOCK 43 - DUPLEX 1 Under Construction
BLOCK 43 - DUPLEX 2 Under Construction
BLOCK 43 - DUPLEX 3 Under Construction
BLOCK 43 - DUPLEX 4 Under Construction
BLOCK 44 - DUPLEX 1 Under Construction
BLOCK 44 - DUPLEX 2 Under Construction
BLOCK 44 - DUPLEX 3 Under Construction
BLOCK 44 - DUPLEX 4 Under Construction
BLOCK 45 - DUPLEX 1 Under Construction
BLOCK 45 - DUPLEX 2 Under Construction
BLOCK 45 - DUPLEX 3 Under Construction
BLOCK 45 - DUPLEX 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Fire Fighting Facilty
4 Use of Renewable Energy

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Entrance
2 Under Construction Lobby
3 Under Construction Lift
4 Under Construction Stairs
5 Under Construction Common Area
6 Under Construction Terrace

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download