New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

BEAUMONDE PHASE - I

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Residential Apartments Booked
    19

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    57

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower A 1 Under Construction
Tower A 2 Not Started
Tower A 3 Not Started
Tower A 4 Not Started
Tower A 5 Not Started
Tower A 6 Not Started
Tower A 7 Not Started
Tower A 8 Not Started
Tower A 9 Not Started
Tower A 10 Not Started
Tower A 11 Not Started
Tower A 12 Not Started
Tower A 13 Not Started
Tower A 14 Not Started
Tower A 15 Not Started
Tower A 16 Not Started
Tower A 17 Not Started
Tower A 18 Not Started
Tower A 19 Not Started
Tower A 20 Not Started
Tower A 21 Not Started
Tower A 22 Not Started
Tower A 23 Not Started
Tower A 24 Not Started
Tower C 1 Under Construction
Tower C 2 Not Started
Tower C 3 Not Started
Tower C 4 Not Started
Tower C 5 Not Started
Tower C 6 Not Started
Tower C 7 Not Started
Tower C 8 Not Started
Tower C 9 Not Started
Tower C 10 Not Started
Tower C 11 Not Started
Tower C 12 Not Started
Tower C 13 Not Started
Tower C 14 Not Started
Tower C 15 Not Started
Tower C 16 Not Started
Tower C 17 Not Started
Tower C 18 Not Started
Tower C 19 Not Started
Tower C 20 Not Started
Tower C 21 Not Started
Tower C 22 Not Started
Tower C 23 Not Started
Tower C 24 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Use of Renewable Energy
2 Drinking Water Facility
3 Emergency Evacuation Services
4 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Lobby
2 Not Started Staircase
3 Not Started Lift
4 Not Started Roof
5 Under Construction Podium
6 Not Started Septic Tank
7 Not Started Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download