Solaris Joka Phase 1 (Revised)

Project Status as on Quarter ending 31-03-2021
Updated as on 04-08-2021

Booking Status

  • Residential Apartments Booked
    259

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    60

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 1 Not Started
2 1 Under Construction
2 2 Not Started
3 1 Under Construction
1 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Piling

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1
2 Under Construction Gate
3 Under Construction
4 Under Construction Piling work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 12-10-2015 12-10-2019 10-12-2015
Consent to Establish and Operate 02-05-2018 03-09-2018 12-10-2018 Clearance of Proposed Construction