New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

Newtown Villas Phase-1

Project Status as on Quarter ending 31-12-2025
Updated as on 06-01-2026

Booking Status

  • Residential Apartments Booked
    28

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1/4k/1 1 Under Construction
1/4k/1 2 Under Construction
1/4k/2 1 Under Construction
1/4k/2 2 Under Construction
1/4k/3 1 Under Construction
1/4k/3 2 Under Construction
1/4K/4 1 Under Construction
1/4K/4 2 Under Construction
1/4K/5 1 Under Construction
1/4K/5 2 Under Construction
1/4K/6 1 Under Construction
1/4K/6 2 Under Construction
1/4K/7 1 Under Construction
1/4K/7 2 Under Construction
1/4K/8 1 Under Construction
1/4K/8 1 Under Construction
1/3K/9 1 Under Construction
1/3K/9 2 Under Construction
1/3K/10 1 Under Construction
1/3K/10 2 Under Construction
1/3K/11 1 Under Construction
1/3K/11 2 Under Construction
1/3K/12 1 Under Construction
1/3K/12 2 Under Construction
1/3K/13 1 Under Construction
1/3K/13 2 Not Started
1/3K/14 1 Under Construction
1/3K/14 2 Under Construction
1/3K/15 1 Under Construction
1/3K/15 2 Under Construction
1/3K/16 1 Under Construction
1/3K/16 2 Under Construction
1/3K/17 1 Under Construction
1/3K/17 2 Under Construction
1/3K/18 1 Under Construction
1/3K/18 2 Under Construction
1/3K/19 1 Under Construction
1/3K/19 2 Under Construction
1/3K/20 1 Under Construction
1/3K/20 2 Under Construction
1/3K/21 1 Under Construction
1/3K/21 2 Under Construction
1/3K/22 1 Under Construction
1/3K/22 2 Under Construction
1/3K/23 1 Under Construction
1/3K/23 2 Under Construction
1/3K/24 1 Under Construction
1/3K/24 2 Under Construction
1/3K/25 1 Under Construction
1/3K/25 2 Under Construction
1/3K/26 1 Under Construction
1/3K/26 2 Under Construction
1/3K/27 1 Under Construction
1/3K/27 2 Under Construction
1/3K/28 1 Under Construction
1/3K/28 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Extinguisher Facility
2 Water Treatment Plant

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Overhead Tank
2 Not Started Stair
3 Not Started Roof
4 Not Started Septic Tank
5 Not Started Lift
6 Not Started Lobby
7 Under Construction Club
8 Under Construction Under Ground Water Reservoir

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download