WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

AMBEY UTSAV

Project Status as on Quarter ending 30-09-2024
Updated as on 07-10-2024

Booking Status

  • Residential Apartments Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    1

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 2 Completed Without CC
A 3 Completed Without CC
A 4 Under Construction
B 1 Completed Without CC
B 2 Under Construction
B 3 Not Started
B 4 Not Started
A 1 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 20-06-2023 30-09-2023 27-09-2023