WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

SHYAM KUNJ PHASE-III

Project Status as on Quarter ending 31-03-2025
Updated as on 07-04-2025

Booking Status

  • Residential Apartments Booked
    18

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    6

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 1 Completed Without CC
BLOCK 1 2 Completed Without CC
BLOCK 1 3 Completed Without CC
BLOCK 1 4 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 plinth
2 floor
3 slab super structure
4 internal wall, Internal Plaster, Flooring, Door and winodos
5 staircase,lift,lobbies at each floor
6 external plumbing and external plaster,elevation, completion of terrace

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction internal road and footpath
2 Under Construction water supply
3 electrical meter room

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download