Solaris City Serampore Phase 1C

Project Status as on Quarter ending 30-09-2024
Updated as on 28-09-2024

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Pilling Work
2 Under Construction Pilling Work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 03-01-2018 03-01-2019 27-01-2020
Such other approvals as may be required and obtained for the project 21-11-2018 28-11-2018 30-11-2018 Mutation Certificate