New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Solaris City Serampore Phase 1C

Project Status as on Quarter ending 30-09-2025
Updated as on 22-09-2025

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
C 2 Not Started
C 3 Not Started
C 4 Not Started
C 5 Not Started
C 6 Not Started
C 7 Not Started
C 8 Not Started
C 9 Not Started
C 10 Not Started
C 11 Not Started
C 12 Not Started
C 13 Not Started
D 2 Not Started
D 3 Not Started
D 4 Not Started
D 5 Not Started
D 6 Not Started
D 7 Not Started
D 8 Not Started
D 9 Not Started
D 10 Not Started
D 11 Not Started
D 12 Not Started
D 13 Not Started
C 1 Under Construction
C 1 Under Construction
D 1 Under Construction
C 1 Under Construction
D 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Pilling Work
2 Under Construction Pilling Work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 03-01-2018 03-01-2019 27-01-2020
Such other approvals as may be required and obtained for the project 21-11-2018 28-11-2018 30-11-2018 Mutation Certificate