WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

PRIME PLAZA

Project Status as on Quarter ending 31-03-2021
Updated as on 16-04-2021

Booking Status

  • Residential Apartments Booked
    6

  • Commercial Unit Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
ONE 1 Under Construction
ONE 2 Under Construction
ONE 3 Under Construction
ONE 4 Under Construction
ONE 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Brickwork Done for First Floor
2 Brickwork Done for Ground Floor
3 Brickwork Done for Second Floor
4 PLASTER GROUND FIRST SECOND THIRD AND FOURTH FLOOR
5 ROOF WORK

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction LOBBY AND LIFT AREA
2 Under Construction LOBBY AND LIFT AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download