New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

SUNFLOWER APARTMENTS

Project Status as on Quarter ending 31-12-2019
Updated as on 14-04-2025

Booking Status

  • Residential Apartments Booked
    7

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 COMPLETED
2 COMPLETIION CERTIFCATE
3 COMPLETION CERTIFICATE
4 FRONT FACE OF THE BUILDING
5 ENTRY GATE TO BUILDING
6 ELECTRIC METER PLACE
7 STAIRCASE
8 STAIRCASE 2
9 ENTRY
10 COMMON PASSAGE
11 ONE OF THE FLAT ENTRY
12 BED ROOM 1
13 BED ROOM 2
14 WASHROOM 1
15 WASHROOM 2
16 KITCHEN CUM DINNING

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC ENTRY AND EXIT
2 Completed With CC ENTRY AND EXIT
3 Completed With CC KITCHEN CUM DINNING
4 Completed With CC ENTRY
5 Completed With CC STAIR CASE 1
6 Completed With CC STAIRCASE 2
7 Completed With CC COMMON PASSAGE
8 Completed With CC THE BUILDING IS FULLY COMPLETE ON 28.02.2020

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 27-01-2020 29-02-2020 28-02-2020 COMPLETION CERTFICATE