Project Status as on Quarter ending 31-03-2024
Updated as on 28-10-2024

Booking Status

  • Residential Apartments Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 1 Not Started
A 2 Not Started
A 3 Not Started
A 4 Not Started
A 5 Not Started
A 6 Not Started
B 1 Under Construction
B 2 Under Construction
B 3 Under Construction
B 4 Under Construction
B 5 Under Construction
B 6 Under Construction
C 1 Not Started
C 2 Not Started
C 3 Not Started
C 4 Not Started
C 5 Not Started
C 6 Not Started
D 1 Under Construction
D 2 Under Construction
D 3 Under Construction
D 4 Under Construction
D 5 Under Construction
D 6 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Stair and Lift Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download