New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

Shukhobrishti Spandan Phase 8

Project Status as on Quarter ending 31-12-2018
Updated as on 17-04-2025

Booking Status

  • Residential Apartments Booked
    934

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
SPANDAN (LIG) PHASE 8 4 Under Construction
SPANDAN (LIG) PHASE 8 4 Under Construction
SPANDAN (LIG) PHASE 8 1 Under Construction
SPANDAN (LIG) PHASE 8 2 Under Construction
SPANDAN (LIG) PHASE 8 3 Under Construction
SPANDAN (LIG) PHASE 8 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal road network
2 Landscaping

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Staircase
2 Under Construction Green open space

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 04-11-2014 16-01-2015 16-01-2015
Consent to Establish and Operate 28-03-2006 22-01-2009 22-01-2009