WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Shukhobrishti Spriha Phase 8

Project Status as on Quarter ending 31-03-2021
Updated as on 02-04-2021

Booking Status

  • Residential Apartments Booked
    554

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
SPRIHA (UMIG) PHASE - 8 1 Under Construction
SPRIHA (UMIG) PHASE - 8 2 Not Started
SPRIHA (UMIG) PHASE - 8 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Road network
2 Road network
3 Internal plumbing work

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 04-12-2014 16-01-2015 16-01-2015
Consent to Establish and Operate 28-03-2006 22-01-2009 22-01-2009