WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

KANIKA APARTMENTS

Project Status as on Quarter ending 30-09-2024
Updated as on 26-07-2024

Booking Status

  • Residential Apartments Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 BEDROOM, BATHROOM, KITCHEN AND VERANDAH

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction STAIRCASE AND LIFT

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download