New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Greenwood Nest

Project Status as on Quarter ending 30-09-2022
Updated as on 28-02-2025

Booking Status

  • Residential Apartments Booked
    485

  • Basement Parking Booked
    137

  • Covered Car Parking Booked
    99

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Alpina 1 1 Completed Without CC
Alpina 1 2 Completed Without CC
Alpina 1 3 Completed Without CC
Alpina 1 4 Completed Without CC
Alpina 1 5 Completed Without CC
Alpina 1 6 Completed Without CC
Alpina 1 7 Completed Without CC
Alpina 1 8 Completed Without CC
Alpina 1 9 Completed Without CC
Alpina 1 10 Completed Without CC
Alpina 1 11 Completed Without CC
Alpina 1 12 Completed Without CC
Alpina 2 1 Completed Without CC
Alpina 2 2 Completed Without CC
Alpina 2 3 Completed Without CC
Alpina 2 4 Completed Without CC
Alpina 2 5 Completed Without CC
Alpina 2 6 Completed Without CC
Alpina 2 7 Completed Without CC
Alpina 2 8 Completed Without CC
Alpina 2 9 Completed Without CC
Alpina 2 10 Completed Without CC
Alpina 2 11 Completed Without CC
Alpina 2 12 Completed Without CC
Alpina 3 1 Completed Without CC
Alpina 3 2 Completed Without CC
Alpina 3 3 Completed Without CC
Alpina 3 4 Completed Without CC
Alpina 3 5 Completed Without CC
Alpina 3 6 Completed Without CC
Alpina 3 7 Completed Without CC
Alpina 3 8 Completed Without CC
Alpina 3 9 Completed Without CC
Alpina 3 10 Completed Without CC
Alpina 3 11 Completed Without CC
Alpina 3 12 Completed Without CC
Maze 1 1 Completed Without CC
Maze 1 2 Completed Without CC
Maze 1 3 Completed Without CC
Maze 1 4 Completed Without CC
Maze 1 5 Completed Without CC
Maze 1 6 Completed Without CC
Maze 1 7 Completed Without CC
Maze 1 8 Completed Without CC
Maze 1 9 Completed Without CC
Maze 1 10 Completed Without CC
Maze 1 11 Completed Without CC
Maze 1 12 Completed Without CC
Maze 2 1 Completed Without CC
Maze 2 2 Completed Without CC
Maze 2 3 Completed Without CC
Maze 2 4 Completed Without CC
Maze 2 5 Completed Without CC
Maze 2 6 Completed Without CC
Maze 2 7 Completed Without CC
Maze 2 8 Completed Without CC
Maze 2 9 Completed Without CC
Maze 2 10 Completed Without CC
Maze 2 11 Completed Without CC
Maze 2 12 Completed Without CC
Lark 1 1 Completed Without CC
Lark 1 2 Completed Without CC
Lark 1 3 Completed Without CC
Lark 1 4 Completed Without CC
Lark 2 1 Completed Without CC
Lark 2 2 Completed Without CC
Lark 2 3 Completed Without CC
Lark 2 4 Completed Without CC
Lark 3 1 Completed Without CC
Lark 3 2 Completed Without CC
Lark 3 3 Completed Without CC
Lark 3 4 Completed Without CC
Lark 3 5 Completed Without CC
Lark 3 6 Completed Without CC
Lark 3 7 Completed Without CC
Lark 3 8 Completed Without CC
Lark 3 9 Completed Without CC
Lark 3 10 Completed Without CC
Lark 3 11 Completed Without CC
Lark 3 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download