Solaris City Serampore Phase 1B

Project Status as on Quarter ending 30-09-2024
Updated as on 28-09-2024

Booking Status

  • Residential Apartments Booked
    37

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    6

  • Mechanical Parking Booked
    2

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 03-01-2018 03-01-2019 27-01-2020
Fire NOC 07-08-2018 24-12-2018 17-01-2019
Environmental Clearance 03-01-2018 03-07-2018 27-01-2020
Consent to Establish and Operate 14-02-2020 06-03-2020 06-03-2020