DAKSHIN DIVINE

Project Status as on Quarter ending 31-03-2025
Updated as on 09-04-2025

Booking Status

  • Residential Apartments Booked
    2

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Image 1
2 Image 2
3 Image 3
4 Image 4
5 Image 7
6 Image 9
7 Image 13
8 Image 14
9 Image 16
10 Image 18
11 Image 19
12 Image 21
13 Foundation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Image 8
2 Under Construction Image 20

Approval for NOC