WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Dakshinee

Project Status as on Quarter ending 31-12-2024
Updated as on 26-01-2025

Booking Status

  • Residential Apartments Booked
    0

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Tank
2 Lift
3 Basement
4 Staircase

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lift Room
2 Under Construction Basement
3 Under Construction Staircase
4 Under Construction Frontage
5 Under Construction Entrance

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 23-01-2025 27-01-2025 24-01-2025 Rera Order Compliance Architect Certificate