WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

UTSODHAARA RESIDENCIA-I

Project Status as on Quarter ending 30-09-2024
Updated as on 07-10-2024

Booking Status

  • Residential Apartments Booked
    185

  • Basement Parking Booked
    90

  • Covered Car Parking Booked
    77

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
PRATHAMA 1 Not Started
PRATHAMA 2 Not Started
PRATHAMA 3 Not Started
PRATHAMA 4 Not Started
PRATHAMA 5 Not Started
PRATHAMA 6 Not Started
PRATHAMA 7 Not Started
PRATHAMA 8 Not Started
PRATHAMA 9 Not Started
PRATHAMA 10 Not Started
PRATHAMA 11 Not Started
PRATHAMA 12 Not Started
PRATHAMA 13 Not Started
DWITIYA 1 Not Started
DWITIYA 2 Not Started
DWITIYA 3 Not Started
DWITIYA 4 Not Started
DWITIYA 5 Not Started
DWITIYA 6 Not Started
DWITIYA 7 Not Started
DWITIYA 8 Not Started
DWITIYA 9 Not Started
DWITIYA 10 Not Started
DWITIYA 11 Not Started
DWITIYA 12 Not Started
DWITIYA 13 Not Started
TRITIYA 1 Not Started
TRITIYA 2 Not Started
TRITIYA 3 Not Started
TRITIYA 4 Not Started
TRITIYA 5 Not Started
TRITIYA 6 Not Started
TRITIYA 7 Not Started
TRITIYA 8 Not Started
TRITIYA 9 Not Started
TRITIYA 10 Not Started
TRITIYA 11 Not Started
TRITIYA 12 Not Started
TRITIYA 13 Not Started
CHATURTHI 1 Not Started
CHATURTHI 2 Not Started
CHATURTHI 3 Not Started
CHATURTHI 4 Not Started
CHATURTHI 5 Not Started
CHATURTHI 6 Not Started
CHATURTHI 7 Not Started
CHATURTHI 8 Not Started
CHATURTHI 9 Not Started
CHATURTHI 10 Not Started
CHATURTHI 11 Not Started
CHATURTHI 12 Not Started
CHATURTHI 13 Not Started
PANCHAMI 1 Not Started
PANCHAMI 2 Not Started
PANCHAMI 3 Not Started
PANCHAMI 4 Not Started
PANCHAMI 5 Not Started
PANCHAMI 6 Not Started
PANCHAMI 7 Not Started
PANCHAMI 8 Not Started
PANCHAMI 9 Not Started
PANCHAMI 10 Not Started
PANCHAMI 11 Not Started
PANCHAMI 12 Not Started
PANCHAMI 13 Not Started
SASHTHI 1 Not Started
SASHTHI 2 Not Started
SASHTHI 3 Not Started
SASHTHI 4 Not Started
SASHTHI 5 Not Started
SASHTHI 6 Not Started
SASHTHI 7 Not Started
SASHTHI 8 Not Started
SASHTHI 9 Not Started
SASHTHI 10 Not Started
SASHTHI 11 Not Started
SASHTHI 12 Not Started
SASHTHI 13 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire control room
2 Public annunciation and evacuation system
3 Solar power provision at designated areas

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Access to lift lobby
2 Not Started 24/7 DG Back up for designated areas
3 Not Started Street lighting
4 Not Started LED light in common area
5 Not Started Internal sewer storm and water supply line
6 Not Started Organic waste composter
7 Not Started Sewage Treatment plant
8 Not Started Water treatment plant
9 Not Started Security System
10 Not Started Building Management System
11 Not Started Residents' Activity Centre
12 Not Started LANDSCAPE
13 Not Started Common terrace area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 19-01-2023 31-10-2023 14-03-2024
Other 23-11-2022 15-04-2024 15-07-2024
Environmental Clearance 21-05-2024 30-07-2024 30-07-2024 Revision