New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     Applications are invited from the eligible and willing persons for the position of (i) Judicial Member of West Bengal Real Estate Appellate Tribunal (WBREAT) and (ii) Member of West Bengal Real Estate Regulatory Authority (WBRERA) Click here to open;    

Vanya Awas - Apartments Phase - I

Project Status as on Quarter ending 31-03-2026
Updated as on 07-04-2026

Booking Status

  • Residential Apartments Booked
    214

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER-A (DAFFODIL) 1 Under Construction
TOWER-A (DAFFODIL) 2 Under Construction
TOWER-A (DAFFODIL) 3 Under Construction
TOWER-B (LILY) 1 Under Construction
TOWER-B (LILY) 2 Under Construction
TOWER-B (LILY) 3 Under Construction
TOWER-C (DAISY) 1 Under Construction
TOWER-C (DAISY) 2 Under Construction
TOWER-C (DAISY) 3 Under Construction
TOWER-D (TULIP) 1 Under Construction
TOWER-D (TULIP) 2 Under Construction
TOWER-D (TULIP) 3 Under Construction
TOWER-E (ROSE) 1 Under Construction
TOWER-E (ROSE) 2 Under Construction
TOWER-E (ROSE) 3 Under Construction
TOWER-A (DAFFODIL) 1 Under Construction
TOWER-A (DAFFODIL) 2 Under Construction
TOWER-A (DAFFODIL) 3 Under Construction
TOWER-B (LILY) 1 Under Construction
TOWER-B (LILY) 2 Under Construction
TOWER-B (LILY) 3 Under Construction
TOWER-C (DAISY) 1 Under Construction
TOWER-C (DAISY) 2 Under Construction
TOWER-C (DAISY) 3 Under Construction
TOWER-D (TULIP) 1 Under Construction
TOWER-D (TULIP) 2 Under Construction
TOWER-D (TULIP) 3 Under Construction
TOWER-E (ROSE) 1 Under Construction
TOWER-E (ROSE) 2 Under Construction
TOWER-E (ROSE) 3 Under Construction
TOWER-A (DAFFODIL) 1 Completed With CC
TOWER-A (DAFFODIL) 2 Completed With CC
TOWER-A (DAFFODIL) 3 Completed With CC
TOWER-B (LILY) 1 Completed With CC
TOWER-B (LILY) 2 Completed With CC
TOWER-B (LILY) 3 Completed With CC
TOWER-C (DAISY) 1 Completed With CC
TOWER-C (DAISY) 2 Completed With CC
TOWER-C (DAISY) 3 Completed With CC
TOWER-D (TULIP) 1 Completed With CC
TOWER-D (TULIP) 2 Completed With CC
TOWER-D (TULIP) 3 Completed With CC
TOWER-E (ROSE) 1 Completed With CC
TOWER-E (ROSE) 2 Completed With CC
TOWER-E (ROSE) 3 Completed With CC
TOWER-A (DAFFODIL) 1 Under Construction
TOWER-A (DAFFODIL) 2 Under Construction
TOWER-A (DAFFODIL) 3 Under Construction
TOWER-B (LILY) 1 Under Construction
TOWER-B (LILY) 2 Under Construction
TOWER-B (LILY) 3 Under Construction
TOWER-C (DAISY) 1 Under Construction
TOWER-C (DAISY) 2 Under Construction
TOWER-C (DAISY) 3 Under Construction
TOWER-D (TULIP) 1 Under Construction
TOWER-D (TULIP) 2 Under Construction
TOWER-D (TULIP) 3 Under Construction
TOWER-E (ROSE) 1 Under Construction
TOWER-E (ROSE) 2 Under Construction
TOWER-E (ROSE) 3 Under Construction
TOWER-A (DAFFODIL) 1 Under Construction
TOWER-A (DAFFODIL) 2 Under Construction
TOWER-A (DAFFODIL) 3 Under Construction
TOWER-B (LILY) 1 Under Construction
TOWER-B (LILY) 2 Under Construction
TOWER-B (LILY) 3 Under Construction
TOWER-C (DAISY) 1 Under Construction
TOWER-C (DAISY) 2 Under Construction
TOWER-C (DAISY) 3 Under Construction
TOWER-D (TULIP) 1 Under Construction
TOWER-D (TULIP) 2 Under Construction
TOWER-D (TULIP) 3 Under Construction
TOWER-E (ROSE) 1 Under Construction
TOWER-E (ROSE) 2 Under Construction
TOWER-E (ROSE) 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN
2 WATER SUPPLY SOURCE FROM BOREWELL
3 LIFT
4 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN
5 WATER SUPPLY SOURCE FROM BOREWELL
6 LIFT
7 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN
8 WATER SUPPLY SOURCE FROM BOREWELL
9 LIFT
10 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN
11 WATER SUPPLY SOURCE FROM BOREWELL
12 LIFT
13 FIRE FIGHTING AND EMERGENCY EVACUATION PLAN
14 WATER SUPPLY SOURCE FROM BOREWELL
15 LIFT

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started STAIRCASES AND CORRIDORS
2 Not Started OPEN TERRACES
3 Not Started SERVICE AREAS/ ROOMS
4 Not Started FITNESS POCKET
5 Not Started YOGA LAWN
6 Not Started KID'S PLAY AREA
7 Not Started ORGANIC GARDEN
8 Not Started BARBEQUE CORNER
9 Not Started BADMINTON COURT
10 Not Started STAIRCASES AND CORRIDORS
11 Not Started OPEN TERRACES
12 Not Started SERVICE AREAS/ ROOMS
13 Not Started FITNESS POCKET
14 Not Started YOGA LAWN
15 Not Started KID'S PLAY AREA
16 Not Started ORGANIC GARDEN
17 Not Started BARBEQUE CORNER
18 Not Started BADMINTON COURT
19 Completed With CC STAIRCASES AND CORRIDORS
20 Completed With CC OPEN TERRACES
21 Completed With CC SERVICE AREAS/ ROOMS
22 Completed With CC FITNESS POCKET
23 Completed With CC YOGA LAWN
24 Completed With CC KID'S PLAY AREA
25 Completed With CC BADMINTON COURT
26 Completed With CC BADMINTON COURT
27 Completed With CC BARBEQUE CORNER
28 Not Started STAIRCASES AND CORRIDORS
29 Not Started OPEN TERRACES
30 Not Started SERVICE AREAS/ ROOMS
31 Not Started FITNESS POCKET
32 Not Started YOGA LAWN
33 Not Started KID'S PLAY AREA
34 Not Started ORGANIC GARDEN
35 Not Started BADMINTON COURT
36 Not Started STAIRCASES AND CORRIDORS
37 Not Started OPEN TERRACES
38 Not Started SERVICE AREAS/ ROOMS
39 Under Construction FITNESS POCKET
40 Under Construction YOGA LAWN
41 Not Started ORGANIC GARDEN
42 Under Construction BARBEQUE CORNER
43 Under Construction BADMINTON COURT
44 Under Construction KID'S PLAY AREA

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Consent to Establish and Operate 18-02-2024 18-03-2024 18-03-2024
Other 01-09-2025 04-09-2025 04-09-2025
Fire NOC 19-12-2025 30-03-2026 30-03-2026
Such other approvals as may be required and obtained for the project 25-09-2025 03-10-2025 07-10-2025 Lift Operation Licence