WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

CABANA

Project Status as on Quarter ending 31-03-2021
Updated as on 02-05-2025

Booking Status

  • Residential Apartments Booked
    9

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    7

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC
1 1 Completed With CC
1 2 Completed With CC
1 3 Completed With CC
1 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 1. AAC Brick work, 2. Internal plaster , 3. Outside plaster , 4. Internal putty , 5. Tiles , 6. External paint in progress
2 ACC BLOCK WORK , INTERNAL PLASTER

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC 1. Granite work in stair , 2. tiles in garage & pavement 3. septic tank & UGR , 5. Lift, 6. Boundary wall paint and grill completed
2 Completed With CC PCC COMPLETED , COMMON OILET, SECURITY ROOM , STAIR HEAD ROOM

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download