New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Panthaniwas Dooars Phase - III

Project Status as on Quarter ending 31-03-2025
Updated as on 15-05-2025

Booking Status

  • Residential Apartments Booked
    73

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 26 - G+3 1 Completed With CC
Block 26 - G+3 2 Completed With CC
Block 26 - G+3 3 Completed With CC
Block 27 - G+3 1 Completed With CC
Block 27 - G+3 2 Completed With CC
Block 27 - G+3 3 Completed With CC
Block 28 - G+3 1 Completed With CC
Block 28 - G+3 2 Completed With CC
Block 28 - G+3 3 Completed With CC
Block 29 - G+3 1 Completed With CC
Block 29 - G+3 2 Completed With CC
Block 29 - G+3 3 Completed With CC
Block 30 - G+3 1 Completed With CC
Block 30 - G+3 2 Completed With CC
Block 30 - G+3 3 Completed With CC
Block 31 - G+3 1 Completed With CC
Block 31 - G+3 2 Completed With CC
Block 31 - G+3 3 Completed With CC
Block 32 - G+3 1 Completed With CC
Block 32 - G+3 2 Completed With CC
Block 32 - G+3 3 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Supply
2 Fire Extinguisher
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lobby
2 Completed With CC Stairs
3 Completed With CC Lift
4 Completed With CC Roof
5 Completed With CC Children park area
6 Completed With CC Club House
7 Completed With CC Common Area
8 Completed With CC Guest house
9 Completed With CC Open Ampitheater
10 Completed With CC Open Gym area
11 Completed With CC Outdoor play area
12 Completed With CC Panthashala restaurant
13 Completed With CC Sitting Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download