WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Larica Green Pailan

Project Status as on Quarter ending 31-03-2021
Updated as on 17-03-2021

Booking Status

  • Residential Apartments Booked
    80

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    12

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
A 3 Under Construction
B 4 Completed Without CC
C 4 Completed Without CC
D 4 Completed Without CC
E 4 Completed Without CC
G 4 Under Construction
H 4 Under Construction
I 4 Under Construction
J 4 Under Construction
L 4 Under Construction
A 3 Under Construction
B 4 Completed Without CC
C 4 Completed Without CC
D 4 Completed Without CC
E 4 Completed Without CC
G 4 Under Construction
H 4 Under Construction
I 4 Under Construction
J 4 Under Construction
L 4 Under Construction
B 5 Under Construction
A 5 Under Construction
C 5 Under Construction
D 5 Under Construction
E 5 Under Construction
G 5 Under Construction
H 5 Under Construction
I 5 Under Construction
J 5 Under Construction
L 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 70% of work completed
2 70% of work completed
3 72% completed
4 Approach road to the Project-1
5 Approched road to the project
6 Approach road to the project
7 Approach road to the project
8 Approach road th the project
9 Road & Water

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction 70% of work completed
2 Under Construction 70% of work completed
3 Under Construction 70% of work completed
4 Under Construction Road and passage
5 Under Construction Renewal Energy, Drainage & Drinking Water

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download