WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Joyville Howrah Tower A1 - Pinnacle

Project Status as on Quarter ending 31-03-2020
Updated as on 03-07-2020

Booking Status

  • Residential Apartments Booked
    105

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    13

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower A1-Pinnacle 19 Completed With CC
Tower A1-Pinnacle 19 Under Construction
Tower A1-Pinnacle 19 Under Construction
Tower A1-Pinnacle 19 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal finish
2 Toilet
3 Club house
4 Club house
5 Parking block
6 Parking block
7 Parking block
8 Parking block

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Environmental Clearance 28-04-2016 03-10-2016 04-10-2016
Consent to Establish and Operate 18-01-2017 07-02-2017 14-02-2017
Fire NOC 16-07-2014 28-11-2014 04-12-2014
Such other approvals as may be required and obtained for the project 26-06-2014 03-07-2014 10-07-2014