WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

KRISHNAM VILLA

Project Status as on Quarter ending 30-09-2025
Updated as on 04-10-2025

Booking Status

  • Residential Apartments Booked
    4

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 LIft, water pump, fire equipment work completed
2 Internal, road, sewage etc. completed
3 BlockA-Lift is 90% completed. BlockB Lift 100% completed
4 Water tank completed
5 Double coat paint pending
6 Entrance gate is pending. Block A- Window Aluminium sliding 20% pending
7 Water supply to Block A Sumbermissibe pump pending
8 Construction till plinth level completed which includes material, labour charges
9 BLOCK A & B- Roof casting done for all floors
10 BLOCK A & B- All floor completed in all respect escept ground floor. For ground floor tiles work is in progress. Lift work in progree. Expecting to fininsh within a short period of time. Brick & plaster work completed. Putty & tiles work is complete
11 BLOCK A & B- All floor completed in all respect escept ground floor. For ground floor tiles work is in progress. Lift work in progree. Expecting to fininsh within a short period of time.Brick & plaster work completed. Putty & tiles work is completed

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common area work completed
2 Under Construction Boundary and Landscaping work done
3 Under Construction Plinth lecel completed for both the blocks
4 Under Construction PCC & boundary work is done. Tiles, paint, electrical, plumbing work in progress.
5 Under Construction PCC & boundary work is done. Tiles & Electrical work completed. Paint, plumbing work in progress.

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download