| 1 |
LIft, water pump, fire equipment work completed |
|
| 2 |
Internal, road, sewage etc. completed |
|
| 3 |
BlockA-Lift is 90% completed. BlockB Lift 100% completed |
|
| 4 |
Water tank completed |
|
| 5 |
Double coat paint pending |
|
| 6 |
Entrance gate is pending. Block A- Window Aluminium sliding 20% pending |
|
| 7 |
Water supply to Block A Sumbermissibe pump pending |
|
| 8 |
Construction till plinth level completed which includes material, labour charges |
|
| 9 |
BLOCK A & B- Roof casting done for all floors |
|
| 10 |
BLOCK A & B- All floor completed in all respect escept ground floor. For ground floor tiles work is in progress. Lift work in progree. Expecting to fininsh within a short period of time. Brick & plaster work completed. Putty & tiles work is complete |
|
| 11 |
BLOCK A & B- All floor completed in all respect escept ground floor. For ground floor tiles work is in progress. Lift work in progree. Expecting to fininsh within a short period of time.Brick & plaster work completed. Putty & tiles work is completed |
|