WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Balaji Residency

Project Status as on Quarter ending 30-06-2024
Updated as on 03-07-2024

Booking Status

  • Residential Apartments Booked
    22

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    2

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block-1 Ground 1 Completed Without CC
Block-1 1 Completed Without CC
Block-1 2 Completed Without CC
Block-1 3 Completed Without CC
Block-1 4 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Lobby
2 Completed Without CC Stairs
3 Completed Without CC Lift
4 Completed Without CC Roof
5 Completed Without CC Septic Tank
6 Completed Without CC Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download