Merlin Aspire

Project Status as on Quarter ending 31-03-2021
Updated as on 16-04-2021

Booking Status

  • Residential Apartments Booked
    183

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 (G+4) 2 Under Construction
BLOCK 1 (G+4) 1 Under Construction
BLOCK 1 (G+4) 3 Under Construction
BLOCK 1 (G+4) 4 Under Construction
BLOCK 1 (G+4) 5 Under Construction
BLOCK 2 (G+4) 1 Under Construction
BLOCK 2 (G+4) 2 Under Construction
BLOCK 2 (G+4) 3 Under Construction
BLOCK 2 (G+4) 4 Under Construction
BLOCK 2 (G+4) 4 Under Construction
BLOCK 2 (G+4) 5 Under Construction
BLOCK 3(G+4) 1 Under Construction
BLOCK 3(G+4) 2 Under Construction
BLOCK 3(G+4) 3 Under Construction
BLOCK 3(G+4) 4 Under Construction
BLOCK 3(G+4) 5 Under Construction
BLOCK 4( G+4) 1 Under Construction
BLOCK 4( G+4) 2 Under Construction
BLOCK 4( G+4) 3 Under Construction
BLOCK 4( G+4) 4 Under Construction
BLOCK 4( G+4) 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drainage and Pipes
2

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download