New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

NEWTOWN VILLAS PHASE-5

Project Status as on Quarter ending 31-12-2025
Updated as on 02-01-2026

Booking Status

  • Residential Apartments Booked
    31

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
5/2.25/159 1 Not Started
5/2.25/159 2 Not Started
5/2.25/160 1 Not Started
5/2.25/160 2 Not Started
5/2.25/161 1 Not Started
5/2.25/161 2 Not Started
5/2.25/162 1 Not Started
5/2.25/162 2 Not Started
5/2.25/163 1 Not Started
5/2.25/163 2 Not Started
5/2.25/164 1 Not Started
5/2.25/164 2 Not Started
5/2.25/165 1 Not Started
5/2.25/165 2 Not Started
5/2.25/166 1 Not Started
5/2.25/166 2 Not Started
5/2.25/167 1 Not Started
5/2.25/167 2 Not Started
5/2.25/168 1 Not Started
5/2.25/168 2 Not Started
5/2.25/169 1 Not Started
5/2.25/169 2 Not Started
5/2.25/170 1 Not Started
5/2.25/170 2 Not Started
5/2.25/171 1 Not Started
5/2.25/171 2 Not Started
5/2.25/172 1 Not Started
5/2.25/172 2 Not Started
5/2.25/173 1 Not Started
5/2.25/173 2 Not Started
5/2.25/174 1 Not Started
5/2.25/174 2 Not Started
5/2.25/175 1 Not Started
5/2.25/175 2 Not Started
5/2.25/176 1 Not Started
5/2.25/176 2 Not Started
5/2.25/177 1 Not Started
5/2.25/177 2 Not Started
5/2.25/178 1 Not Started
5/2.25/178 2 Not Started
5/2.25/179 1 Not Started
5/2.25/179 2 Not Started
5/2.25/180 1 Not Started
5/2.25/180 2 Not Started
5/2.25+/187 1 Not Started
5/2.25+/187 2 Not Started
5/2.25+/188 1 Not Started
5/2.25+/188 2 Not Started
5/2.25+/189 1 Not Started
5/2.25+/189 2 Not Started
5/2.25+/190 1 Not Started
5/2.25+/190 2 Not Started
5/2.25+/191 1 Not Started
5/2.25+/191 2 Not Started
5/2.25+/192 1 Not Started
5/2.25+/192 2 Not Started
5/2.25+/193 1 Not Started
5/2.25+/193 2 Not Started
5/2.25+/194 1 Not Started
5/2.25+/194 2 Not Started
5/2.25+/195 1 Not Started
5/2.25+/195 2 Not Started
5/2.25+/196 1 Not Started
5/2.25+/196 2 Not Started
5/2.25+/197 1 Not Started
5/2.25+/197 2 Not Started
5/2.25+/198 1 Not Started
5/2.25+/198 2 Not Started
5/3/136 1 Not Started
5/3/136 2 Not Started
5/3/137 1 Not Started
5/3/137 2 Not Started
5/3/138 1 Not Started
5/3/138 2 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Extinguisher Facility
2 Water Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Stairs
2 Not Started Roof
3 Not Started Club
4 Not Started Septic Tank
5 Not Started Under-Ground Water Reservoir
6 Not Started Lift
7 Not Started Lobby

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download