New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

SUNILALO APARTMENT

Project Status as on Quarter ending 31-12-2025
Updated as on 31-12-2025

Booking Status

  • Residential Apartments Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
2 2 Completed Without CC
1 2 Completed Without CC
2 2 Completed Without CC
1 1 Completed Without CC
2 3 Completed Without CC
2 1 Under Construction
1 2 Under Construction
1 1 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Outside painting work done
2 Common passage work completed
3 Project completed without CC
4 Building completed in all respect except CC for which application already submitted to the authority for CC
5 Roof casting done. Brick work completed. Inside & Outside plaster completed. Tiles work completed. Electrical work done. lift work in progress.
6 Roof casting done. Brick work completed. Inside & Outside plaster completed. Tiles work completed. Electrical work done. lift work in progress. For Block 1- Outside colour is pending and lift work under progress. For Block 2-only lift work is pending
7 Project completed and waiting for Completion Certificate
8 Excavation completed
9 Plinth level completed for Block 1 and 2
10 Roof casting for both Block 1 and 2 completed. Internal wall, plaster almost 80% completed
11 Roof casting done. Brick work completed. Inside & Outside plaster completed. Tiles work completed. Electrical work done. lift work in progress.

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Building completed in all respect except CC for which application already submitted to the authority for CC
2 Under Construction Work done except For Block 1- Outside colour is pending and lift work under progress. For Block 2-only lift work is pending
3 Completed Without CC Project work completed and waiting for CC

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download