WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

DONA TWINS - RAIMA

Project Status as on Quarter ending 31-12-2024
Updated as on 12-04-2025

Booking Status

  • Residential Apartments Booked
    5

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Ground Floor 1 Under Construction
1st to 3rd floor 1 Under Construction
1st to 3rd floor 2 Under Construction
1st to 3rd floor 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Main Gate
2 Under Construction Lobby
3 Under Construction Stair Case
4 Not Started Lift
5 Under Construction Roof
6 Under Construction Power backup
7 Under Construction Septic Tank

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download