Project Status as on Quarter ending 31-03-2025
Updated as on 03-04-2025

Booking Status

  • Residential Apartments Booked
    34

  • Commercial Unit Booked
    5

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    14

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 1 Under Construction
Block 1 2 Under Construction
Block 1 3 Under Construction
Block 1 4 Under Construction
Block 1 Commercial 1 Under Construction
Block 2 G+4 1 Under Construction
Block 2 G+4 2 Under Construction
Block 2 G+4 3 Under Construction
Block 2 G+4 4 Under Construction
Block 3 G+4 1 Under Construction
Block 3 G+4 2 Not Started
Block 3 G+4 3 Not Started
Block 3 G+4 4 Not Started
Block 4 G+4 1 Under Construction
Block 4 G+4 2 Under Construction
Block 4 G+4 3 Under Construction
Block 4 G+4 4 Not Started
Block 5 G+4 1 Under Construction
Block 5 G+4 2 Under Construction
Block 5 G+4 3 Under Construction
Block 5 G+4 4 Under Construction
Block 6 G+4 1 Under Construction
Block 6 G+4 2 Under Construction
Block 6 G+4 3 Under Construction
Block 6 G+4 4 Under Construction
Block 7 1 Under Construction
Block 7 2 Under Construction
Block 7 3 Under Construction
Block 7 4 Under Construction
Block 8 G+4 1 Under Construction
Block 8 G+4 2 Not Started
Block 8 G+4 3 Under Construction
Block 8 G+4 4 Under Construction
Block 9 G+4 1 Under Construction
Block 9 G+4 2 Not Started
Block 9 G+4 3 Not Started
Block 9 G+4 4 Not Started
Block 10 1 Not Started
Block 10 2 Not Started
Block 10 3 Not Started
Block 10 4 Not Started
Block 10 Commercial 1 Not Started
Block 11 Commercial 1 Not Started
Block 11 1 Not Started
Block 11 2 Not Started
Block 11 3 Not Started
Block 11 4 Not Started
Block 12 Commercial 1 Not Started
Block 12 1 Not Started
Block 12 2 Not Started
Block 12 3 Not Started
Block 12 4 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facility
2 Emergency Evacuation Services
3 Use of Renewable Energy
4 Roof Top Garden

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Main Gate
2 Under Construction Lobby
3 Under Construction Lift
4 Under Construction Stairs
5 Not Started Jogging Track & Morning Walk Zone
6 Not Started Senior Citizens Sitting Arrangements
7 Not Started Beautification Of Pond
8 Not Started Children's Park
9 Not Started Basket Ball Play Area
10 Not Started Community Hall
11 Not Started Indor Play Room
12 Under Construction Roof
13 Not Started Gym

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download