WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Sunrise Aura Phase I

Project Status as on Quarter ending 30-09-2024
Updated as on 09-10-2024

Booking Status

  • Residential Apartments Booked
    241

  • Basement Parking Booked
    86

  • Covered Car Parking Booked
    74

  • Mechanical Parking Booked
    78

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
8 18 Not Started
3 1 Under Construction
3 2 Under Construction
3 3 Under Construction
3 4 Under Construction
3 5 Under Construction
3 6 Under Construction
3 7 Under Construction
3 8 Under Construction
3 9 Under Construction
3 10 Under Construction
3 11 Under Construction
3 12 Under Construction
3 13 Under Construction
3 14 Under Construction
3 15 Under Construction
3 16 Under Construction
3 17 Not Started
3 18 Not Started
3 19 Not Started
3 20 Not Started
4 1 Under Construction
4 2 Under Construction
4 3 Under Construction
4 4 Under Construction
4 5 Under Construction
4 6 Under Construction
4 7 Under Construction
4 8 Under Construction
4 9 Under Construction
4 10 Under Construction
4 11 Under Construction
4 12 Under Construction
4 13 Under Construction
4 14 Under Construction
4 15 Under Construction
4 16 Under Construction
4 17 Under Construction
4 18 Under Construction
4 19 Under Construction
4 20 Under Construction
5 1 Under Construction
5 2 Under Construction
5 3 Under Construction
5 4 Under Construction
5 5 Under Construction
5 6 Under Construction
5 7 Under Construction
5 8 Under Construction
5 9 Under Construction
5 10 Under Construction
5 11 Under Construction
5 12 Under Construction
5 13 Under Construction
5 14 Under Construction
5 15 Under Construction
5 16 Under Construction
5 17 Under Construction
5 18 Under Construction
8 1 Under Construction
8 2 Under Construction
8 3 Under Construction
8 4 Under Construction
8 5 Under Construction
8 6 Under Construction
8 7 Under Construction
8 8 Under Construction
8 9 Under Construction
8 10 Under Construction
8 11 Under Construction
8 12 Under Construction
8 13 Under Construction
8 14 Under Construction
8 15 Under Construction
8 16 Under Construction
8 17 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting facilities
2 Electrical Facility

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Club
2 Under Construction Lobby
3 Under Construction Stairs
4 Under Construction Roof
5 Under Construction Lift
6 Under Construction Septic Tank
7 Under Construction Overhead Tank
8 Under Construction Sanitary & Plumbing Facility

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download