WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

IMPERIAL RIDDHI SIDDHI

Project Status as on Quarter ending 31-03-2021
Updated as on 12-04-2021

Booking Status

  • Residential Apartments Booked
    100

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    53

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
RUBY 1 Under Construction
RUBY 2 Under Construction
RUBY 3 Under Construction
RUBY 4 Under Construction
RUBY 5 Under Construction
TOPAZ 1 Under Construction
TOPAZ 2 Under Construction
TOPAZ 3 Under Construction
TOPAZ 4 Under Construction
TOPAZ 5 Under Construction
EMERALD 1 Under Construction
EMERALD 2 Under Construction
EMERALD 3 Under Construction
EMERALD 4 Under Construction
EMERALD 5 Under Construction
SAPPHIRE 1 Under Construction
SAPPHIRE 2 Under Construction
SAPPHIRE 3 Under Construction
SAPPHIRE 4 Under Construction
SAPPHIRE 5 Under Construction
KOHINOOR 1 Completed Without CC
KOHINOOR 3 Completed Without CC
KOHINOOR 2 Completed Without CC
KOHINOOR 4 Completed Without CC
KOHINOOR 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Internal Infrastructure

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction As per the plan sanction construction is going on.
2 Under Construction Elevation all Bock
3 Under Construction Swimming Pool

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download