New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

MONUJ

Project Status as on Quarter ending 31-12-2023
Updated as on 30-04-2025

Booking Status

  • Residential Apartments Booked
    2

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Tower B 1 Under Construction
Tower B 2 Under Construction
Tower B 3 Under Construction
Tower B 4 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Reinforced Cement Concrete Work
2 Bricks Work

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction water reserve tank
2 Under Construction Deep Tubewall
3 Under Construction Pilling

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Consent to Establish and Operate 01-02-2021 16-03-2021 16-03-2021 Sanction of erection of the building and issue of building permit under Rule 21
Fire NOC 05-03-2018 07-03-2018 07-03-2018 Fire Permission
Permission from Water and Sewerage department 05-01-2021 22-03-2021 22-03-2021 Jet Pump permission