WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

ANANYA

Project Status as on Quarter ending 31-12-2025
Updated as on 05-01-2026

Booking Status

  • Residential Apartments Booked
    15

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    2

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Completed Without CC
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 1 Completed Without CC
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 1 Completed Without CC
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 4 Under Construction
1 6 Under Construction
1 1 Completed Without CC
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 BASEMENT GARAGE
2 GROUND FLOOR COMMERCIAL
3 FIRST FLOOR COMMERCIAL
4 SECOND FLOOR RESIDENTIAL
5 THIRD FLOOR RESIDENTIAL
6 FOURTH FLOOR RESIDENTIAL
7 INTERNAL INFRASTRUCTURE
8 FLOORWISE
9 BASEMENT
10 GROUND AND FIRST FLOOR
11 2ND TO 5TH FLOOR
12 5TH FLOOR

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Drinking Water facility for worker
2 Completed Without CC Drinking Water facility for worker
3 Completed Without CC Drinking Water facility for worker
4 Completed Without CC Drinking Water facility for worker
5 Completed Without CC Drinking Water facility for worker
6 Completed Without CC Drinking Water facility for worker
7 Completed Without CC Labour Hutment area
8 Completed Without CC DRINKING WATER AND LABOUR HUTMENT
9 Under Construction INTERNAL ROAD AND OTHERS

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Height clearance from Airport Authority of India (if any) 08-05-2023 11-05-2023 11-05-2023 NONE
Such other approvals as may be required and obtained for the project 09-07-2024 05-10-2024 05-10-2024 AMENDMENT