Project Status as on Quarter ending 30-09-2024
Updated as on 24-10-2024

Booking Status

  • Residential Apartments Booked
    35

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
SUNSTONE 1 Not Started
SUNSTONE 2 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Common Infrastructure Works

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started Common Area Works

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download