WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Annapurna Apartment

Project Status as on Quarter ending 31-12-2024
Updated as on 28-10-2024

Booking Status

  • Residential Apartments Booked
    6

  • Commercial Unit Booked
    1

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    4

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 STAIRCASE

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download