WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    NO OFFLINE APPLICATIONS WILL BE ACCEPTED ON AND FROM 15.12.2025     

Siddha Esplanade - Phase I

Project Status as on Quarter ending 31-12-2020
Updated as on 20-02-2025

Booking Status

  • Commercial Unit Booked
    52

  • Basement Parking Booked
    9

  • Covered Car Parking Booked
    62

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK - A 1 Completed With CC
BLOCK - A 2 Completed With CC
BLOCK - A 3 Completed With CC
BLOCK - A 4 Completed With CC
BLOCK - A 5 Completed With CC
BLOCK - A 6 Completed With CC
BLOCK - A 7 Completed With CC
BLOCK - A 8 Completed With CC
BLOCK - A 9 Completed With CC
BLOCK - A 10 Completed With CC
BLOCK - A 11 Completed With CC
BLOCK - A 12 Completed With CC
BLOCK - A 13 Completed With CC
BLOCK - A 14 Completed With CC
BLOCK - A 15 Completed With CC
BLOCK - A 16 Completed With CC
BLOCK - A 17 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Lift
2 Completed With CC Lobby
3 Completed With CC Overhead Tank
4 Completed With CC Roof
5 Completed With CC Power Backup

Approval for NOC