WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Siddha Esplanade - Phase I

Project Status as on Quarter ending 31-12-2023
Updated as on 04-04-2024

Booking Status

  • Commercial Unit Booked
    52

  • Basement Parking Booked
    9

  • Covered Car Parking Booked
    62

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK - A 1 Completed Without CC
BLOCK - A 2 Completed Without CC
BLOCK - A 3 Completed Without CC
BLOCK - A 4 Completed Without CC
BLOCK - A 5 Completed Without CC
BLOCK - A 6 Completed Without CC
BLOCK - A 7 Completed Without CC
BLOCK - A 8 Completed Without CC
BLOCK - A 9 Completed Without CC
BLOCK - A 10 Completed Without CC
BLOCK - A 11 Completed Without CC
BLOCK - A 12 Completed Without CC
BLOCK - A 13 Completed Without CC
BLOCK - A 14 Completed Without CC
BLOCK - A 15 Completed Without CC
BLOCK - A 16 Completed Without CC
BLOCK - A 17 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Lift
2 Completed Without CC Lobby
3 Completed Without CC Overhead Tank
4 Completed Without CC Roof
5 Completed Without CC Power Backup

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download