New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

SHYAM TOWER

Project Status as on Quarter ending 30-09-2024
Updated as on 14-05-2025

Booking Status

  • Residential Apartments Booked
    31

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    12

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Commercial Units 1 Completed Without CC
Block - 1 - 1st to 3rd Floor 1 Completed Without CC
Block - 1 - 1st to 3rd Floor 2 Completed Without CC
Block - 1 - 1st to 3rd Floor 3 Completed Without CC
Block 2 - 1st to 11th Floor 1 Completed Without CC
Block 2 - 1st to 11th Floor 2 Completed Without CC
Block 2 - 1st to 11th Floor 3 Completed Without CC
Block 2 - 1st to 11th Floor 4 Completed Without CC
Block 2 - 1st to 11th Floor 5 Completed Without CC
Block 2 - 1st to 11th Floor 6 Completed Without CC
Block 2 - 1st to 11th Floor 7 Completed Without CC
Block 2 - 1st to 11th Floor 8 Completed Without CC
Block 2 - 1st to 11th Floor 9 Completed Without CC
Block 2 - 1st to 11th Floor 10 Completed Without CC
Block 2 - 1st to 11th Floor 11 Completed Without CC
Block 2 - 12th Floor 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drinking Water Facilities
2 Emergency Evacuation
3 Fire Fighting Facilty

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Lobby
2 Completed Without CC Staircase
3 Completed Without CC Lift
4 Completed Without CC Terrace
5 Completed Without CC Main Gate

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download