New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Solaris City Serampore Phase 2

Project Status as on Quarter ending 30-09-2025
Updated as on 22-09-2025

Booking Status

  • Residential Apartments Booked
    0

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    Not mentioned

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
11 1 Not Started
11 2 Not Started
11 3 Not Started
11 4 Not Started
11 5 Not Started
11 6 Not Started
11 7 Not Started
11 8 Not Started
11 9 Not Started
11 10 Not Started
11 11 Not Started
11 12 Not Started
11 1 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Not Started

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Consent to Establish and Operate 12-11-2013 13-06-2013 13-06-2013
Fire NOC 17-01-2019 17-01-2019 17-01-2019
Other 12-11-2013 13-06-2016 13-06-2016