WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    The last date for all the pending quarterly project updates has been extended till 30.04.2025,please upload all the pending quarterly updates within 30.04.2025 to avoid penalty.

GOPAL BHAWAN

Project Status as on Quarter ending 31-03-2025
Updated as on 06-04-2025

Booking Status

  • Residential Apartments Booked
    13

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    3

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 under Construction
2 UNDER CONDTRUCTION
3 PROJECT IS COMPLETE AND READY TO HAND OVER

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction under construction
2 Under Construction UNDER CONSTRUCTION
3 Completed Without CC COMPLETE
4 Under Construction Under construction

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download