WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

Merlin The One

Project Status as on Quarter ending 30-09-2024
Updated as on 05-10-2024

Booking Status

  • Residential Apartments Booked
    384

  • Basement Parking Booked
    163

  • Covered Car Parking Booked
    154

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER 1 (B+G+17) 1 Completed With CC
TOWER 1 (B+G+17) 2 Completed With CC
TOWER 1 (B+G+17) 3 Completed With CC
TOWER 1 (B+G+17) 4 Completed With CC
TOWER 1 (B+G+17) 5 Completed With CC
TOWER 1 (B+G+17) 6 Completed With CC
TOWER 1 (B+G+17) 7 Completed With CC
TOWER 1 (B+G+17) 8 Completed With CC
TOWER 1 (B+G+17) 9 Completed With CC
TOWER 1 (B+G+17) 10 Completed With CC
TOWER 1 (B+G+17) 11 Completed With CC
TOWER 1 (B+G+17) 12 Completed With CC
TOWER 1 (B+G+17) 13 Completed With CC
TOWER 1 (B+G+17) 14 Completed With CC
TOWER 1 (B+G+17) 15 Completed With CC
TOWER 1 (B+G+17) 16 Completed With CC
TOWER 1 (B+G+17) 17 Completed With CC
TOWER 1 (B+G+17) 18 Completed With CC
TOWER 2 (B+G+17) 1 Completed With CC
TOWER 2 (B+G+17) 2 Completed With CC
TOWER 2 (B+G+17) 3 Completed With CC
TOWER 2 (B+G+17) 4 Completed With CC
TOWER 3 (B+G+17) 5 Completed With CC
TOWER 2 (B+G+17) 6 Completed With CC
TOWER 2 (B+G+17) 7 Completed With CC
TOWER 2 (B+G+17) 8 Completed With CC
TOWER 2 (B+G+17) 9 Completed With CC
TOWER 2 (B+G+17) 10 Completed With CC
TOWER 2 (B+G+17) 11 Completed With CC
TOWER 2 (B+G+17) 12 Completed With CC
TOWER 2 (B+G+17) 13 Completed With CC
TOWER 2 (B+G+17) 14 Completed With CC
TOWER 2 (B+G+17) 15 Completed With CC
TOWER 2 (B+G+17) 16 Completed With CC
TOWER 2 (B+G+17) 17 Completed With CC
TOWER 2 (B+G+17) 18 Completed With CC
TOWER 3 (B+G+17) 1 Completed With CC
TOWER 3 (B+G+17) 2 Completed With CC
TOWER 3 (B+G+17) 3 Completed With CC
TOWER 3 (B+G+17) 4 Completed With CC
TOWER 3 (B+G+17) 5 Completed With CC
TOWER 3 (B+G+17) 6 Completed With CC
TOWER 3 (B+G+17) 7 Completed With CC
TOWER 3 (B+G+17) 8 Completed With CC
TOWER 3 (B+G+17) 9 Completed With CC
TOWER 3 (B+G+17) 10 Completed With CC
TOWER 3 (B+G+17) 11 Completed With CC
TOWER 3 (B+G+17) 12 Completed With CC
TOWER 3 (B+G+17) 13 Completed With CC
TOWER 3 (B+G+17) 14 Completed With CC
TOWER 3 (B+G+17) 15 Completed With CC
TOWER 3 (B+G+17) 16 Completed With CC
TOWER 3 (B+G+17) 17 Completed With CC
TOWER 3 (B+G+17) 18 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Drainage and Pipes

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Common Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download