WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

FLORA FOUNTAIN

Project Status as on Quarter ending 31-03-2021
Updated as on 08-04-2021

Booking Status

  • Residential Apartments Booked
    282

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    281

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
1 1 Under Construction
1 2 Under Construction
1 3 Under Construction
1 4 Under Construction
1 5 Under Construction
1 6 Under Construction
1 7 Under Construction
1 8 Under Construction
1 9 Under Construction
1 10 Under Construction
1 11 Under Construction
1 12 Under Construction
1 13 Under Construction
1 14 Under Construction
1 15 Under Construction
1 16 Under Construction
1 17 Under Construction
1 18 Under Construction
1 19 Under Construction
1 20 Under Construction
1 21 Under Construction
1 22 Under Construction
1 23 Under Construction
1 24 Under Construction
2 1 Under Construction
2 2 Under Construction
2 3 Under Construction
2 4 Under Construction
2 5 Under Construction
2 6 Under Construction
2 7 Under Construction
2 8 Under Construction
2 9 Under Construction
2 10 Under Construction
2 11 Under Construction
2 12 Under Construction
2 13 Under Construction
2 14 Under Construction
2 15 Under Construction
2 17 Under Construction
2 18 Under Construction
2 19 Under Construction
2 20 Under Construction
2 21 Under Construction
2 22 Under Construction
2 23 Under Construction
2 24 Under Construction
1 3 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Block - 1
2 Block- 2
3 POND

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Landscale
2 Under Construction Swimming Pool
3 Under Construction Block - 1
4 Under Construction Block- 2
5 Under Construction Podium
6 Under Construction MAIN GATE
7 Under Construction Internal Roads
8 Under Construction Parking

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 20-08-2019 31-03-2020 16-06-2020 AMENDMENT OF SANCTION PLAN