New Promoters are requested to refer the user manual for Quarterly Project Status Update Click here to open;    Extension of validity of the project registration under section 7 (3) of the Real Estate (Regulation and Development) Act, 2016 Click here to open;    Order Regarding Advertisement and other Publicities of Registered Projects Click here to open;    Project Extension Certificate will be issued only after the payment of penalty imposed by the WBRERA Authority    Notice inviting Quotation (NIQ) from reliable agencies for carrying out publicity about WBRERA activities on various social media platforms. Click here to open;    

Siddha Suburbia

Project Status as on Quarter ending 31-12-2022
Updated as on 10-03-2025

Booking Status

  • Residential Apartments Booked
    391

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    391

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
CAMELIA - 1A 1 Completed With CC
CAMELIA - 1A 2 Completed With CC
CAMELIA - 1A 3 Completed With CC
CAMELIA - 1A 4 Completed With CC
CAMELIA - 1A 5 Completed With CC
CAMELIA - 1A 6 Completed With CC
CAMELIA - 1A 7 Completed With CC
CAMELIA - 1A 8 Completed With CC
CAMELIA - 1A 9 Completed With CC
CAMELIA - 1A 10 Completed With CC
CAMELIA - 1A 11 Completed With CC
CAMELIA - 1A 12 Completed With CC
CAMELIA - 1A 13 Completed With CC
CAMELIA - 1A 14 Completed With CC
DAHLIA - 1B 1 Completed With CC
DAHLIA - 1B 2 Completed With CC
DAHLIA - 1B 3 Completed With CC
DAHLIA - 1B 4 Completed With CC
DAHLIA - 1B 5 Completed With CC
DAHLIA - 1B 6 Completed With CC
DAHLIA - 1B 7 Completed With CC
DAHLIA - 1B 8 Completed With CC
DAHLIA - 1B 9 Completed With CC
DAHLIA - 1B 10 Completed With CC
DAHLIA - 1B 11 Completed With CC
DAHLIA - 1B 12 Completed With CC
DAHLIA - 1B 13 Completed With CC
DAHLIA - 1B 14 Completed With CC
EUPHORIA - 1C 1 Completed With CC
EUPHORIA - 1C 2 Completed With CC
EUPHORIA - 1C 3 Completed With CC
EUPHORIA - 1C 4 Completed With CC
EUPHORIA - 1C 5 Completed With CC
EUPHORIA - 1C 6 Completed With CC
EUPHORIA - 1C 7 Completed With CC
EUPHORIA - 1C 8 Completed With CC
EUPHORIA - 1C 9 Completed With CC
EUPHORIA - 1C 10 Completed With CC
EUPHORIA - 1C 11 Completed With CC
EUPHORIA - 1C 12 Completed With CC
EUPHORIA - 1C 13 Completed With CC
EUPHORIA - 1C 14 Completed With CC
FLORENCIA - 1E 1 Under Construction
FLORENCIA - 1E 2 Under Construction
FLORENCIA - 1E 3 Under Construction
FLORENCIA - 1E 4 Under Construction
FLORENCIA - 1E 5 Under Construction
FLORENCIA - 1E 6 Under Construction
FLORENCIA - 1E 7 Under Construction
FLORENCIA - 1E 8 Under Construction
FLORENCIA - 1E 9 Under Construction
FLORENCIA - 1E 10 Under Construction
FLORENCIA - 1E 11 Under Construction
FLORENCIA - 1E 12 Under Construction
FLORENCIA - 1E 13 Under Construction
FLORENCIA - 1E 14 Under Construction
GARDENIA - 1F 1 Under Construction
GARDENIA - 1F 2 Under Construction
GARDENIA - 1F 3 Under Construction
GARDENIA - 1F 4 Under Construction
GARDENIA - 1F 5 Not Started
GARDENIA - 1F 6 Not Started
GARDENIA - 1F 7 Not Started
GARDENIA - 1F 8 Not Started
GARDENIA - 1F 9 Not Started
GARDENIA - 1F 10 Not Started
GARDENIA - 1F 11 Not Started
GARDENIA - 1F 12 Not Started
GARDENIA - 1F 13 Not Started
GARDENIA - 1F 14 Not Started
HALONIA - 1G 1 Completed With CC
HALONIA - 1G 2 Completed With CC
HALONIA - 1G 3 Completed With CC
HALONIA - 1G 4 Completed With CC
HALONIA - 1G 5 Completed With CC
HALONIA - 1G 6 Completed With CC
HALONIA - 1G 7 Completed With CC
HALONIA - 1G 8 Completed With CC
HALONIA - 1G 9 Completed With CC
HALONIA - 1G 10 Completed With CC
HALONIA - 1G 11 Completed With CC
HALONIA - 1G 12 Completed With CC
HALONIA - 1G 13 Completed With CC
HALONIA - 1G 14 Completed With CC
AMBROSIA - 1H 1 Completed With CC
AMBROSIA - 1H 2 Completed With CC
AMBROSIA - 1H 3 Completed With CC
AMBROSIA - 1H 4 Completed With CC
AMBROSIA - 1H 5 Completed With CC
AMBROSIA - 1H 6 Completed With CC
AMBROSIA - 1H 7 Completed With CC
AMBROSIA - 1H 8 Completed With CC
AMBROSIA - 1H 9 Completed With CC
AMBROSIA - 1H 10 Completed With CC
AMBROSIA - 1H 11 Completed With CC
AMBROSIA - 1H 12 Completed With CC
AMBROSIA - 1H 13 Completed With CC
AMBROSIA - 1H 14 Completed With CC
BEGONIA - 1J 1 Completed With CC
BEGONIA - 1J 2 Completed With CC
BEGONIA - 1J 3 Completed With CC
BEGONIA - 1J 4 Completed With CC
BEGONIA - 1J 5 Completed With CC
BEGONIA - 1J 6 Completed With CC
BEGONIA - 1J 7 Completed With CC
BEGONIA - 1J 8 Completed With CC
BEGONIA - 1J 9 Completed With CC
BEGONIA - 1J 10 Completed With CC
BEGONIA - 1J 11 Completed With CC
BEGONIA - 1J 12 Completed With CC
BEGONIA - 1J 13 Completed With CC
BEGONIA - 1J 14 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Solar Energy
2 Fire Fighting Facilities
3 Solar Energy
4 Fire Fighting Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Skywalk
2 Completed With CC Power Backup
3 Completed With CC Sewage Treatment Plant
4 Completed With CC Water Treatment Facility
5 Completed With CC Kids Play Area
6 Completed With CC Skywalk
7 Completed With CC Power Backup
8 Completed With CC Sewage Treatment Plant
9 Completed With CC Water Treatment Facility
10 Completed With CC Kids Play Area

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Such other approvals as may be required and obtained for the project 13-07-2017 23-08-2019 25-03-2019