WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

JIVA HOMES

Project Status as on Quarter ending 31-12-2020
Updated as on 02-03-2021

Booking Status

  • Residential Apartments Booked
    79

  • Basement Parking Booked
    26

  • Covered Car Parking Booked
    17

  • Mechanical Parking Booked
    65

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
BLOCK 1 9 Under Construction
BLOCK 2 9 Under Construction
BLOCK 2 3 Under Construction
BLOCK 4A 9 Under Construction
BLOCK 4B 3 Under Construction
BLOCK 4B 9 Under Construction
BLOCK 2 1 Under Construction
BLOCK 3 1 Under Construction
BLOCK 1 6 Under Construction
BLOCK 2 7 Under Construction
BLOCK 4B 5 Under Construction
BLOCK 1 1 Under Construction
BLOCK 2 2 Under Construction
BLOCK 4A 1 Under Construction
BLOCK 4B 1 Under Construction
BLOCK 1 3 Under Construction
BLOCK 2 1 Under Construction
BLOCK 2 5 Under Construction
BLOCK 4A 3 Under Construction
BLOCK 4B 2 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 CENTRAL POND
2 UGR RCC WORK
3 STP RCC WORK
4 POND
5 STP

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction BLOCK-4A 8TH FLOOR LIFT LOBBY
2 Under Construction BLOCK-2,3RD FLOOR LIFT LOBBY
3 Under Construction BLOCK-4B,8TH FLOOR LIFT LOBBY
4 Under Construction liftwell at block -2
5 Under Construction liftwell at block -2
6 Under Construction BLOCK 4B-STAIRS
7 Under Construction BLOCK 2,6TH FLOOR STAIR LOBBY
8 Under Construction BLOCK 4A-STAIR AND LIFT LOBBY
9 Under Construction BLOCK-2 STAIRS

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download